Here is the schedule update from Webster Paving as of June 7.
The road areas have been cleaned in preparation for the repair work. They will be delivering stone and equipment today and Monday. Monday / Tuesday stone will be added to the roads in need of repair and then oil will be applied to the stone on Thursday / Friday to adhere it to the road. Of course, weather permitting.
The oiled road surface can be drive on after the application. Please drive very slowly for a few weeks.
The crew will fold in the sidewalk sealing work in the next 2 weeks. Please do not walk on the side walk for 24 HOURS.